Kaduna River Crossing
A 340-metre, seven-span reinforced concrete bridge with approach embankments, river training works and scour protection.
Location
Kaduna State
Client
State Ministry of Infrastructure
Period
2022–2024
Contract Value
₦9.7bn
The Challenge
What made this project difficult
Deep alluvial deposits and seasonal flooding required foundations to be installed within a strictly limited low-water window.
The Solution
How we delivered it
Bored piles to 34 metres were installed from temporary causeways built ahead of the season, with precast deck elements fabricated off-site to compress on-river activity.
Technology Used
- 34m bored pile foundations
- Precast deck segments
- Elastomeric bearing systems
- Hydrological scour modelling
Impact
- Two communities connected year-round
- Detour of 55km eliminated
- Zero lost-time injuries recorded